Completed large-scale construction project

Representative Experience

Project
Portfolio

A selection of representative engagements across five sectors. Every project handled directly — no junior staff, no handoffs.

01
Commercial·Office / Mixed-Use
$185M
Northeast

Urban Office Tower

420,000 SF

EstimatingCost Management

Full preconstruction estimating and owner-side cost management for a 28-story Class A office tower with ground-floor retail. Scope included three design-phase estimates, bid analysis and leveling across 42 trade packages, and change order review through construction completion.

Highlights

  • Three milestone estimates from SD through CD
  • Bid leveling across 42 trade packages
  • Change order review — $4.2M in contractor claims resolved
  • Final cost within 1.8% of GMP
02
Institutional·Higher Education
$220M
Mid-Atlantic

University Science & Engineering Complex

310,000 SF

EstimatingSchedulingPreconstruction

Preconstruction cost planning and CPM scheduling for a new science and engineering complex on an active campus. Phased construction required detailed sequencing analysis to maintain campus operations. Value engineering facilitation identified $14M in scope reductions without compromising program.

Highlights

  • Phased CPM schedule across 4 construction stages
  • Value engineering — $14M in savings identified
  • Constructability review flagged 23 coordination issues pre-bid
  • Delivered on time and within the approved capital budget
03
Healthcare·Medical Center
$148M
Southeast

Regional Medical Center Expansion

195,000 SF

EstimatingCost Management

Independent cost estimating and owner-side cost management for a major hospital expansion including a new surgical suite, ICU, and patient tower addition. Highly complex MEP systems and infection control requirements demanded detailed systems-level estimating beyond standard assemblies.

Highlights

  • Systems-level MEP estimating for surgical and ICU suites
  • Infection control premium quantified and tracked separately
  • Owner contingency managed across 36-month construction period
  • Change order audit recovered $2.8M in unsupported markups
04
Residential·Multi-Family
$92M
Mid-Atlantic

Mixed-Income Housing Development

380 units / 8 buildings

EstimatingPreconstruction

Feasibility-through-bid estimating for a large mixed-income residential development across eight buildings. Early-phase cost modeling informed financing structure and unit mix decisions. Bid package preparation and contractor prequalification support delivered a competitive bid environment.

Highlights

  • Feasibility cost model supported tax credit financing application
  • Unit mix optimization based on cost-per-unit analysis
  • Bid packages structured to maximize local contractor participation
  • Low bid 4.1% below owner budget — no scope reductions required
05
Industrial·Manufacturing / Warehouse
$165M
Midwest

Advanced Manufacturing Facility

650,000 SF

EstimatingSchedulingCost Management

Full-service estimating, scheduling, and cost management for a greenfield advanced manufacturing facility with heavy process equipment, specialized utility infrastructure, and a compressed 22-month delivery schedule. Schedule analysis identified critical path risks that were resolved through procurement strategy adjustments.

Highlights

  • Process equipment and utility infrastructure estimated separately from building shell
  • Critical path analysis identified 6-week schedule risk — resolved pre-award
  • Long-lead procurement strategy developed and tracked
  • Project delivered 3 weeks ahead of schedule
06
Civic·Public / Government
$210M
Northeast

Municipal Justice Center

280,000 SF

EstimatingSchedulingPreconstructionCost Management

All four service disciplines engaged for a new municipal justice center delivered via design-build. Independent owner-side representation throughout design-build procurement, design development, and construction. Provided the owner with an independent check on the design-builder's cost and schedule reporting at every milestone.

Highlights

  • Independent estimate at each design-build milestone
  • Design-builder's GMP validated within 2.3%
  • Schedule review identified 11-week float erosion — corrective action taken
  • Full-service owner representation through certificate of occupancy

Project details are representative of the type and scale of work performed. Specific client names, exact locations, and proprietary cost data are withheld in accordance with client confidentiality. Project values reflect total construction cost at completion.

Your project
could be next.

Whether you're in feasibility or mid-construction, independent cost expertise pays for itself. Let's talk about what you're working on.

Construction Cost Consulting

Independent construction estimating and cost management services for architects, engineers, contractors, and developers.

40 Years of Precision

Services

  • Construction Estimating
  • Project Scheduling
  • Preconstruction Services
  • Cost Management